Build-Up and Dismantle Scheduling at European Exhibition Venues
The build-up window at a tier-one European fair is a finite resource with hard hand-back deadlines and EUR 1,000-3,000 per day overrun penalties.
What has been corrected on this page?
Every accepted correction to this page is recorded with the exact change, so readers can see how the page improved over time.
-
AUMA does not publish a document called an 'exhibitor manual' - this is an unverified title for a citation. FAMAB Verband Direkte Wirtschaftskommunikation is an outdated organization name; it rebranded in 2021 to 'fwd: Bundesvereinigung Veranstaltungswirtschaft e.V.' and famab.de now redirects to forward.live.
Before- AUMA exhibitor manual (2024-2026 edition), Association of the German Trade Fair Industry, [auma.de](https://www.auma.de)
After- AUMA, "Successful Trade Fair Participation" guide, Association of the German Trade Fair Industry, [auma.de](https://www.auma.de)
Why: 2 issues fixed: AUMA does not publish a document called an 'exhibitor manual' - this is an unverified title for a citation. | FAMAB Verband Direkte Wirtschaftskommunikation is an outdated organization name; it rebranded in 2021 to 'fwd: Bundesvereinigung Veranstaltungswirtschaft e.V.' and famab.de now redirects to forward.live.
View the full record →
Who checked this page?
1 contributor has checked "Build-Up and Dismantle Scheduling at European Exhibition Venues" on Exhibition Stands EU. Each name below links to that person's public CitePep profile, where every contribution they have made is listed with the exact change they proposed.